At the 2021 Census, 99.2% of occupied homes in the suburb of Melbourne, which covers the CBD and the St Kilda Road area, were flats or apartments, and 59.9% had no registered motor vehicle. That is why EV charger installation Melbourne CBD work starts with the building rather than the car. In an established tower, one basement serves every lot, the main switchboard was sized long before anyone planned for chargers, and an owners corporation or building manager has to agree before a cable moves. Our CBD premises is at 185–187 Bourke Street in the Hoddle Grid, about 140 metres from the Russell Street corner, and a city job with us begins with a walk through the car park and a look at the main switchboard.
EV charger installation Melbourne CBD: the basement comes first
Our A-grade electricians want three answers first: how much spare capacity the main switchboard has, where your lot’s meter and distribution board sit compared with your car space, and how many other owners are likely to want charging soon.
There are two broad ways to feed a car space. The first is a dedicated circuit from your own apartment’s supply, run through the risers to your bay. Your existing meter records the energy, so billing looks after itself, but in a tower that run can be long. Length drives cable size: 6 mm² is the usual cable for a 32 amp single-phase charger, and a long riser run can push that to 10 mm². The second is a shared EV distribution board in the car park, fed from the main switchboard, with a sub-meter for each charger and load management sharing the capacity between cars.
We reckon a shared backbone wins once more than a handful of owners want to charge. Every one-off circuit takes riser space and switchboard capacity the next owner might need, and the committee ends up having the same debate every few months. If the main switchboard is the bottleneck, start with our notes on switchboard upgrades for EV chargers.
Taking it to the owners corporation
In most towers the cable route crosses common property, so the owners corporation is involved from day one. The Owners Corporations Act 2006 sets the ground rules. Under section 52, any “significant alteration to the use or appearance of the common property” needs a special resolution, except where the maintenance plan already allows it or it is agreed under section 53.
To pass a special resolution you need 75% of the total votes at a meeting, or 75% of total lot entitlements if it goes to a ballot or poll. Fall short at the meeting and there is a fallback: an interim special resolution, backed by at least 50% of votes with 25% or fewer against, becomes a special resolution 29 days on, unless a petition from owners holding over a quarter of the votes stops it.
One clause we would not lean on: section 138B. It protects “sustainability items” on a lot’s exterior from unreasonable bans, but the definition’s examples are solar hot water, solar panels and roof colours, with no mention of EV chargers.
In August 2026 the state published an EV-ready guide for owners corporations, and its advice is to settle an EV strategy first rather than assume one technical fix, or an immediate install, suits every building. Fair enough. For a committee, our owners corporation EV charging service covers what that conversation needs:
- spare capacity at the main switchboard and in the car park’s supply
- cable routes, board locations and charger positions marked on the car park plan
- how each charger is metered and how costs are recovered
- the load management method, and whether a CitiPower application is needed

Four city car parks, four different first questions
Not every CBD job is a residential tower. The building type changes what we check first and who signs off.
| Building | First question | Who signs off |
|---|---|---|
| Existing apartment tower | Is there spare capacity at the main switchboard, and how far is each bay from its lot’s supply? | Owners corporation, plus the lot owner |
| Newer apartment building | Were EV-dedicated boards and a charging control system built in under NCC 2022? | The builder until handover, then the owners corporation |
| Office tenancy car spaces | Does the lease cover the bays, and how is the building’s peak demand managed? | Landlord or building manager, with the tenant |
| Public or commercial car park | How will drivers pay, and who sells the electricity? | The operator |
Renting adds a step. Most households in the suburb rent: 71.0% of occupied homes at the 2021 Census. If yours is one of them, your rental provider is the first call, since the lot owner is the one who takes the request to the owners corporation.
Office towers and commercial car parks
New office buildings arrive with some groundwork done. Under clause J9D4 of NCC 2022, car parks serving offices and most other building classes need EV-only distribution boards, and every one of them must link to a charging control system that schedules charging against the building’s total consumption. The Australian Building Codes Board’s J9D4 guide explains that 10% of the car spaces attached to a Class 5 office building must be EV ready, with each circuit able to supply 12 kWh or more across the 9 am to 5 pm working day. Chargers do not have to be fitted from day one, and stand-alone Class 7a car parks are exempt.
Older office car parks bring more people into the decision: the tenant who wants bays for staff or pool cars, the landlord, and the building manager who controls access and work hours. We prefer hardware that supports OCPP, the open protocol the Open Charge Alliance publishes for chargers and management software, so a car park is not tied to one software supplier when a lease changes hands.
For staff and pool cars, our fleet and workplace EV charging service is the better starting point, while retail and mixed-use sites sit with our commercial EV charger installation team.
What the City of Melbourne is asking of new car parks
The City of Melbourne is pushing the same way through its planning scheme. Amendment C376melb would add electric vehicle infrastructure provisions to the Capital City Zone schedules for the central city, including the Retail Core. As exhibited in 2023, it asks that car parks in new developments include the electricity supply, space and metering to support charging points. Facilities with 50 or more spaces would also provide EV-ready bays for at least 5% of non-shared spaces, capacity for charging at 20% of spaces, and charging points at all allocated shared car spaces.
An independent panel supported those provisions in October 2024, and Council adopted the amendment in July 2025. On 12 October 2026 the state planning register still listed it as awaiting approval, so it is not law yet. If you are designing a new car park in the grid, plan for it anyway.
Existing buildings face a related squeeze. The City’s Electrifying Apartment Buildings program with the Victorian Government offers electrification feasibility studies for up to 10 strata buildings, running from September 2026 to March 2027. It is not about cars, but the Victorian Service and Installation Rules list EV chargers alongside air conditioning and induction cooktops as equipment that can trigger a supply upgrade. Plan them together and you may only need to upgrade once.
CitiPower and the order of work
The 3000 postcode sits in CitiPower’s network, which covers Melbourne’s CBD and inner suburbs. If the building needs a bigger or different supply, CitiPower’s supply alteration process applies: the application must be made by a registered electrical contractor, and every job needs a Certificate of Electrical Safety. CitiPower expects most alterations to take three to eight weeks, while high-capacity EV charging installations and dedicated on-site substations may need its separate network upgrade process.
Order matters. The Victorian Service and Installation Rules advise customers not to spend money on equipment that could disturb the network until the distributor has seen an application and responded. Our order on a city job:
- Walk the car park, risers and main switchboard with building management.
- Calculate spare capacity and draw up a load management plan.
- Put the proposal to the owners corporation, landlord or operator.
- Submit any supply alteration to CitiPower through its eConnect portal.
- Install, then run the mandatory tests before energising, RCD operation among them.
- Hand over the Certificate of Electrical Safety, then commission metering and the charger app.
Chargers that suit a shared car park
Most apartment owners do not need the biggest charger available. CitiPower’s guide is 30 to 40 km of driving for every hour a 7 kW single-phase unit is plugged in, so a few hours overnight covers a lot of city kilometres. Going to 22 kW needs three-phase power plus a car able to accept that rate; the Polestar 2, for one, is specified for 11 kW AC on three-phase.
In a shared basement we also look at:
- Protection. Since 1 May 2023, new Australian installations cannot use Type AC RCDs, which may miss the pulsating DC leakage a charger can produce. Whether we choose Type A or Type B depends on the DC fault detection built into the charger.
- Cable style. Tethered units come with a fixed lead; untethered units have a socket and the driver brings the cable. In a busy basement, a fixed lead hung on a holster keeps the floor clear.
- Access and billing. Chargers that lock to a user and log each session against a sub-meter.
Got a charger from your car dealer? We install customer-supplied units too, provided the model suits the building’s supply and management system, and we repair and service existing ones.

Frequently asked questions from CBD owners corporations and building managers
How long does it take if CitiPower needs to change the supply?
CitiPower’s own estimate for most alterations is three to eight weeks, depending on complexity, with delays if appointments are missed or field visits fail.
Does a new apartment building already have EV charging?
Not necessarily. Clause J9D4 of NCC 2022 asks for EV-only boards linked to a charging control system in car parks serving apartment buildings, designed so 7 kW Type 2 chargers can be added later, but nobody has to fit the chargers at the start. Older buildings usually have neither.
Can the owners corporation charge residents for the electricity their cars use?
Yes. Section 12 of the Owners Corporations Act 2006 lets it provide a service by special resolution and recover the cost from users. Selling electricity for EV charging is exempt from licensing under the Essential Services Commission’s General Exemption Order 2022, with an annual report due by 31 March.
Should a city car park have 22 kW chargers?
Rarely. They need a three-phase supply, they eat capacity the rest of the building may need, and the extra power only helps cars whose onboard charger can accept it. A load-managed 7 kW circuit is usually the better use of the supply.
Book a car park walk-through
We are part of DUKE Electrical Group and work under REC 35838 from 185–187 Bourke Street, open Monday to Saturday between 7am and 7pm. For a quote, phone 1300 003 853 or send the building details through our online contact page. Homes in the inner south-east are closer to our South Yarra premises on Toorak Road.